Project Description
The J74 VW Transporter All Body Shop Lines Revision Project was executed at Ford Otosan Yeniköy Plant as a comprehensive robot modernization and system upgrade program. This was not a turnkey installation, but a large-scale revision covering multiple body shop lines.
The project focused on replacing chronically problematic old-generation ABB and KUKA robots used in spot welding, sealing, and handling applications. A total of 95 industrial robots were included in the scope. The first 40 old-series ABB robots were replaced with new ABB units. The remaining 55 robots were converted from legacy KUKA/ABB systems to KUKA KRC4-based robot platforms.
All robot programs and trajectories were recreated and validated in simulation to match the previous production geometry and process logic, ensuring seamless transition without impacting dimensional quality. In-house robot systems were commissioned on site and fully integrated with existing line equipment and communication infrastructure.
The lines continue operating at a 115-second cycle time in compliance with PL-d safety standards. The project was completed within 6 months, achieving the targeted production quality levels, with 24/7 standby technical support provided during the stabilization period.

Case Details
- Client
- Ford Otosan
- Project Type
- Multi-Line Revision & Robot Modernization
- Application
- Body Shop Welding, Sealing & Handling Lines
- Location
- Turkey
- Project Duration
- 6 Months
- Safety Level
- PL-d
Important Facts
- Comprehensive body shop-wide robot modernization project
- 95 industrial robots upgraded and recommissioned
- 40 old-generation ABB robots replaced with new ABB units
- 55 robots converted to KUKA KRC4-based control systems
- Robot trajectories recreated to match previous production geometry
- Simulation-based validation before commissioning (Siemens Process Simulate)
- On-site integration with existing automation and communication systems
- 115-second production cycle maintained
- PL-d compliant safety architecture
- Quality targets achieved after commissioning
- 24/7 technical standby support during stabilization phase